Living Construction Projects Santa Monica Blvd. Project
Santa Monica Blvd Reconstruction Project
 Santa Monica Boulevard Segment 2 Photo
Segment 2 facing west at Crescent Drive - Four-lane configuration
 
 
 North Santa Monica Boulevard Reconstruction Project 

July 10, 2018 - August 31, 2018
(Schedule subject to changes)
Thank you for your patience!

WEEKLY UPDATE (Subject to schedule changes)

Traffic Impacts - During paving, streets will be closed to thru traffic. In addition there will be lane closures along North Santa Monica Blvd. to accommodate the paving operations.

Construction Activity – Paving Alpine Drive, Elm Drive and Hillcrest Drive. Removing the raised median at the intersection of North Santa Monica Blvd and replacing with asphalt. During that time, there will be lane closures on Beverly Blvd. south of North Santa Monica Blvd. to accommodate this work.

Work Hours: 7am - 6pm 

5.21.18 Construction Notice

SMBLVD Notice 6-14-18

May 2018 SMBLVD Construction Notice

If you have any questions, please call the project helpline at 424-339-9033

The Project will reconstruct a segment (approximately 1.5 miles) of North Santa Monica Boulevard extending from Wilshire Boulevard to Doheny Drive in the City of Beverly Hills. The project will rebuild the deteriorating roadway; upgrade the storm drain system, replace curb and gutters; upgrade access ramps to American with Disability Access (ADA) standards; and install new LED street lights. Enhancements to the roadway include the installation of a bioswale on the north side, landscaping improvements, and widening the south side between Canon Drive and Wilshire Boulevard. Raised crosswalks will be installed on the north side of the boulevard at the unsignalized intersections that connect Beverly Gardens Park.

The City Council formed a 15-member Blue Ribbon Committee in 2013 to conduct public outreach and develop recommendations for the project design.  The Traffic and Parking Commission developed recommendations for traffic mitigation a the request of the City Council.  

Below is a video that provides a brief background of the project.

 

 

CONSTRUCTION ACTIVITIES

The City has awarded a contract to the lowest responsible bidder, Griffith Company, for the North Santa Monica Boulevard Reconstruction Project and an agreement with Berg and Associates, inc. for construction management services on July 19, 2016. Construction began in January 2017 and is scheduled for completion in the Spring of 2018, several months ahead of schedule.  

 

 COMMUNITY AND TRAFFIC MITIGATION MEETINGS

Staff provided an update to the City Council on October 10, 2017 regarding the Santa Monica Boulevard Reconstruction Project. You can view the meeting presentation and other documents by clicking on the links below:

 

SMBlvd Helpline: (424) 339-9033
Email: smblvd@beverlyhills.org

 

 


 

 

  • Press Release - Contruction on Final Segment of NSMB Reconstruction Underway